INTRODUCTION
Project Features
Large scale: Leachate inventory exceeding one million tons
Difficulty: The conductivity of raw water and ammonia nitrogen are extremely high, and the discharge standard is "Emission Standard of Pollutants for Urban Sewage Treatment Plants" GB18918-2002 Grade A
Tight schedule: 800 tons / day completed in one month, 2100 tons / day completed in 3 months
High efficiency: Jiarong uses 18 sets of container leachate treatment equipment to successfully complete the effluent quality and quantity requirements
New model: Adopt Jiarong self-investment equipment and charge according to the water treatment service
time:
Contract signed on March 30, 2018
800 tons / day of water on April 30, 2018
2100 tons / day of water on June 26, 2018
On September 27, 2019, a phase of 940,000 tons of water was realized